Project : Ammonia Evaporator Replacement Project

Client: Wesfarmers CSBP, Western Australia

Completed: May, 2013

Project Highlights:

  • Reduction of 20% in total cost of ownership to CSBP
  • Engineering and equipment supply under one roof resulting in great time saving as a result of reduced interfacing
  • Total fabrication tonnage of 14 tons
  • Fabrication of one Shell and Tube Heat Exchanger, completed record time of 4 months
  • Approval by Worksafe Australia
  • Fabrication at our Partner facilities located in Baroda, India
  • Inspection by Lloyds Register
  • Manufacturing Documentation (MDR) in compliance with AS1210

Project Description

CSBP, Kwinana discovered in January 2013 that Ammonia Evaporator had deteriorated beyond repairs and required to be replaced in the shutdown planned in Late July, 2013.

The Ammonia Evaporator is a Heat Exchanger with 760 tubes, requiring precise fabrication work and specialised welding skills. The Heat Exchanger was fabricated with full radiography testing. Access Petrotec was given the target completion schedule of 3 months which was met due to efficient planning and work schedule by our partner facility in India.

Access Petrotec was awarded the contract in February 2013 and the consignment was delivered to the shipping agency in May 2013, well ahead of time for the shutdown.

CSBP_Heat Exchr_Ammonia Evaporator Project