Project Highlights:
- Monthly Progress Report with status of the project and each deliverable submitted to BHP.
- Manufacturing Documentation (MDR) incompliance with BHP standards and specifications.
Project Description:
BHP was facing operational issues in the underground firewater/deluge system due to inadequate flow and pressure in the Fire Water piping System, Access Petrotec got engaged to carry out the detailed design of firewater supply storage tanks and piping complying with BHP guidelines and specifications.
Project Deliverables: 1. Detail Design & engineering of Fire Water System
- Basis of Design study
- Option Select phase.
- Definition phase Engineering
- Detail design of firewater storage tanks and piping
- Sizing and Selection of valves, tanks, and piping.
- Developed GA drawings, P&ID, Isometrics, civil, and structural drawings.
- Project Management Services for Construction support.

Project Information
- Categories: Industrial Construction (SMP) Services
- Client: BHP Nickel West
- Type: Fire Water System ‐ Detail Design Engineering
- Location: Leinster, WA